A bracket on an industrial gearbox drawing calls for six bolts, and the engineering bill of materials (eBOM) carries them as a single line. The manufacturing bill of materials (mBOM) issues two of those bolts at the station that hangs the bracket and the other four at the station that closes the cover. A change to the bolt grade is then one edit for engineering and two kit changes for every plant that builds the gearbox. Engineers meet the eBOM vs mBOM difference first as that multiplication, which compounds when one engineering change has to be carried out separately at each plant or operation it reaches. Every requirement behind the change should still trace to the original eBOM line, including through the station kits and phantom assemblies that the mBOM built from it and that no requirement ever named.
Design change control is where the two structures meet, and the eBOM-to-mBOM restructuring is the point in that process where a change's intent is easiest to drop. This guide covers what each bill of materials (BOM) contains, how manufacturing engineering derives the mBOM and how a requirement change follows it onto the shop floor. Later sections take up what baselines, variants and a software bill of materials (SBOM) do to alignment. The BOM management chapter handles the wider product-data controls.
What Separates an Engineering BOM From a Manufacturing BOM
The two structures differ in which fields each one fills and which team owns changes to it. Setting those differences side by side shows what manufacturing adds or reorganizes, and where engineering intent can fall out along the way.
Contents and Ownership
An eBOM is the product as designed, owned by product engineering and usually held in product lifecycle management (PLM). The mBOM is the product as built, restructured by manufacturing engineering for enterprise resource planning (ERP) and manufacturing execution system (MES) tools, which sit at the business-planning and manufacturing-operations levels of the ISA-95 enterprise-control integration standard. On the manufacturing side, process or industrial engineering often holds the mBOM. Where it gets built varies too, since some manufacturers derive it inside ERP from PLM master data and others build it alongside a bill of process in a separate manufacturing planning system.
At field level, the eBOM describes form, fit and function through designed parts and the subassemblies that group them. Each part carries the standard and tolerance it was designed to, along with reference designators and the exact design quantity with no scrap allowance. Large subassemblies often have nested eBOMs of their own, so a printed circuit board or a robotic arm sits inside the higher-level structure as a complete structure. Fields the plant needs, such as the ERP part number or the processing time, stay blank because the design team has no reason to fill them.
Manufacturing engineering then adds what the released design leaves out, starting with the assembly sequence and the fasteners, labels, packaging and process consumables the line draws on. Quantities grow to cover scrap allowance and attrition, and the planning fields the eBOM left empty get filled, including references to the tooling and fixtures each operation uses. The result follows assembly routing and stops matching the computer-aided design (CAD) tree. A product can carry several mBOMs, one for each plant or production method. Each one is what buyers and the shop floor work from in ERP and MES, and logistics plans against the same records.
mBOM vs eBOM, Attribute by Attribute
The handoff changes structure, quantities, planning fields and variant handling along with ownership, and reviewers can use the table as a triage guide. An mBOM line with no eBOM parent should fit the Includes row as a fastener, label, consumable or packaging item, or the Planning fields row as a planning entry. A line that fits neither needs a recorded production reason.
| Attribute | eBOM | mBOM |
| Purpose | Control form, fit and function | Control assembly routing and production inputs |
| Created in | Design and engineering phase | Manufacturing planning phase, after design release |
| Owner | Product engineering | Manufacturing engineering |
| Structure | Functional, mirrors the CAD tree | Sequential, mirrors assembly routing |
| Source system | CAD, electronic design automation (EDA), PLM | ERP, MES |
| Quantities | Exact design quantity | Design quantity, plus allowances for scrap and attrition |
| Includes | Designed parts, materials, drawings | Everything in the eBOM plus fasteners, consumables, labels and packaging |
| Planning fields | Left blank | ERP number, line manning, processing time, process instructions, references to tooling and fixtures |
| Variants | One design structure, possibly configurable | Alternate BOMs per plant or production method |
A quantity above the design quantity plus its scrap allowance, or a designed part moved out of its subassembly, is where legitimate restructuring turns into unexplained divergence. Both surface only in a line-by-line comparison of the two structures.
Why Neither BOM Can Replace the Other
For anything past a simple assembly, each structure answers a question the other leaves open, so neither can stand in for the other. Neither says why each item exists or which test verifies it. Traceability holds that record, and after restructuring it has to follow each eBOM item down to every mBOM line it became.
How and When the mBOM Is Derived From the eBOM
Manufacturing engineers create the mBOM after design release, and the gate that authorizes it differs by industry. ISO 13485:2016 is incorporated by reference into 21 CFR Part 820, the Quality Management System Regulation (QMSR), so for Class II, Class III and the listed Class I medical devices the gate is design transfer under Clause 7.3.8, a written procedure confirming that design outputs can be manufactured before they become production specifications. A common pattern keeps one master BOM as a design output inside the design history file (DHF), which the standard calls the design and development file, and seeds the production BOM in ERP from it once transfer is complete.
Restructuring the Released Design
Every edit made while restructuring is a production decision about how a design element gets realized in the structure the plant builds from. The edits with the largest traceability consequence re-parent designed parts. A kit grouping can move a part under an assembly engineering never drew, and the requirement allocated to that part then has to be followed to its new parent. Make-or-buy calls reshape the structure again, because each bought line ends at a supplier part number with no components below it. Phantom assemblies and process consumables are added in the same pass, before the bill of process assigns each mBOM line to an operation and a station, where cycle time and tooling get planned.
How the team executes the handoff decides whether the eBOM revision stays traceable from the plant floor. Comparing the mBOM against the eBOM revision it should match exposes the first four recurring failures below, and a regrouping with no recorded reason, the fifth, leaves nothing to compare:
- A hand-keyed first mBOM: Retyping an eBOM export into ERP makes the first production structure only as accurate as the person keying it and the export they worked from, which may already be stale. Automating the transfer removes the retyping, and the output still needs an accountable reviewer checking what the automation produced.
- Plant edits nobody coordinated: Two plants building the same nominal product can end up kitting the same fasteners at different stations, because each site edited its own mBOM without telling the other.
- An engineering change order (ECO) that stops at the eBOM: Engineering can close an approved ECO on its side with no matching manufacturing change ever opened, and each such ECO adds another difference between two structures that both pass their own release checks.
- An mBOM with no recorded parent revision: Alignment only means something against a named eBOM revision. An mBOM that no longer records which revision it came from leaves teams claiming a match they have no way to show.
- A regrouping with no recorded reason: Manufacturing sometimes regroups a kit or substitutes a part without writing down why. A reviewer a year later can see the edit in the mBOM history and has no way to tell whether it was intended.
A comparison catches the first four only when someone runs it on every change, so it belongs inside the change workflow itself. The fifth has no check of that kind, and the only protection is a reason recorded against the mBOM line when manufacturing makes the edit.
Controlling the Handoff
Control sits in the engineering change workflow, with the eBOM-to-mBOM comparison written into it as a required gate. The manufacturing update waits at that gate, and only a signed-off comparison releases it to the bill of process and the electronic work instructions. On defense programs, drift between the two structures also meets a formal checkpoint. A physical configuration audit examines the as-built configuration of an item against its technical documentation, as MIL-HDBK-61A, since superseded by MIL-HDBK-61B, defines it. An mBOM that has drifted from the baselined eBOM can surface there as a discrepancy between what was built and what the drawings and specifications say.
Where the eBOM and mBOM Diverge in Complex Regulated Hardware
An item can exist in one structure and not the other when phantoms regroup designed parts, or when process materials bring in items that engineering never listed. Plant-specific sourcing goes further and turns one design into several downstream structures, each with its own history.
Phantom Assemblies
Manufacturing teams use phantom assemblies to organize the build around subassemblies that are physically built on the line but rarely stocked. Material planning passes requirements straight through a phantom to its components, though it usually still nets any occasional on-hand stock of the phantom itself. Take a motor controller enclosure that the eBOM carries as one subassembly. If the line assembles it across three stations, the mBOM can break it into three phantom kits, one per station. For the requirement allocated to the enclosure, the realization now lives in three kits the plant rarely, if ever, stocks.
Two sites can also treat the same material differently, one configuring it as a phantom and the other stocking it as a subassembly. Either is a legitimate manufacturing call, and either way one eBOM subassembly ends up represented differently at each site with the design untouched. A phantom nobody manages explicitly can drop or misstate a component engineering meant to track, because material planning runs on the production structure. At the site that keeps the subassembly as a phantom, the phantom is the only place engineering's grouping survives.
Consumables, Packaging, Tooling and Fixtures
The mBOM carries the materials the process consumes. Solder paste, adhesives, lubricants, protective coatings and cleaning agents enter the product structure when manufacturing engineering adds them, with the quantities and attrition rates the plant expects. Consumables carry compliance weight of their own, since an approved supplier or a grade specification for a coating can be as tightly controlled as a designed part.
Packaging and its instructions travel with the shipped product and usually first appear in the mBOM. Tooling and fixtures sit in a different place, because they are resources the bill of process assigns to operations, and the mBOM carries only references to them.
A material-compatibility or surface-cleanliness requirement can be met by an adhesive or coating that appears only in the mBOM. The verification evidence for that design requirement then sits on an item that engineering never listed, so a trace that links the requirement to the eBOM and stops there leaves that evidence orphaned.
Plant-Specific Variants, Alternates and Substitutes
Each plant's mBOM encodes a sourcing strategy, and two plants building the same product can follow different ones. Alternate and substitute parts reflect multi-sourcing and end-of-life notices, with design intent unchanged. Procurement BOMs often live in yet another system with their own revision rules, so an alternate approved there may never appear in PLM. One product therefore fans out into several plant-specific mBOMs, each with its own substitution history. PBOM means the procurement BOM on some teams and a flattened production BOM kept in ERP on others, so a program's documents should say which meaning they use.
The fan-out shows up in the change process as arithmetic. When one engineering change notice (ECN) reaches three plants, manufacturing usually opens a separate change notice at each of them. Plant-level notices like these are commonly called manufacturing change notices (MCNs), though the name varies by system. Each MCN is another place the same engineering change can be applied differently.
When a component reaches end of life or a supplier update arrives incomplete, a part gets substituted. The substitution then has to be traced back through every requirement, risk item and test case the old part supported. "Without recorded links," the BOM management chapter warns, "someone walks that chain by hand, and a missed link stays hidden until the next audit."
How a Requirement Change Travels From the eBOM to the Shop Floor
Configuration control takes every change to released configuration documentation through identification, documentation, impact evaluation, approval, incorporation and verification, in the definition MIL-HDBK-61A gave before MIL-HDBK-61B replaced it. Defense programs send Class I engineering changes, which touch approved performance requirements or affect cost, schedule, safety, interoperability or interchangeability, to a configuration control board (CCB) and route Class II changes through a simpler approval path. Whichever path a change takes, its package has to carry the affected requirement, the product structure, the effectivity and the verification obligations through every handoff.
What a Complete Engineering Change Order Carries
A complete ECO carries five kinds of content, and an ECO that reaches manufacturing engineering missing any of them forces someone downstream to guess. Each guess becomes another regrouping with no recorded reason, the one handoff failure no eBOM-to-mBOM comparison can catch. Written for the manufacturing engineer who has to scope the mBOM change, the five look like this:
- Affected items and rationale: Every component and drawing the change touches is named, with redlines attached and the engineering reason stated, so manufacturing can tell which mBOM lines inherit the change and why.
- Effectivity: The package names the first unit, lot or date the change applies to, in a form that resolves to serial-numbered end items. Each plant then knows which builds take the old structure and which take the new one.
- Inventory disposition: Parts already in stock or in process each get an explicit fate, whether that means using them as they are, reworking or scrapping them, or returning them to the supplier. Any retest or revalidation the reworked parts need before they ship is named too.
- Actions by function: Each affected function gets a named task in the package, and the drawing, work-instruction, inspection and sourcing updates are listed along with any supplier notification or training the change triggers.
- Approvals and verification: Signatures carry dates and comments. The package also sets the verification method and success criteria and schedules an effectiveness check with a named owner.
Material requirements planning buys material against the old design if it runs before the revised structure, its effectivity, the disposition calls and the open-order decisions are all in the controlled system. ISO 13485 Clause 7.3.9, incorporated through 21 CFR 820.10(c), adds a review obligation before any of that for Class II, Class III and the listed Class I medical devices. The review has to evaluate effects on constituent parts and on product already delivered or still in process, so the mBOM and inventory consequence gets scoped during approval. In a May 9, 2025 warning letter, the U.S. Food and Drug Administration (FDA) cited NeuroSync, Inc. over a software fix it never verified. The letter found that the company failed to "identify, document, validate or where appropriate verify, review, and approve of design changes before their implementation," a Quality System Regulation requirement that the QMSR replaced on February 2, 2026.
The Path From Change Request to Work Instruction
Tools differ between programs, and the stages a controlled change passes through still follow the same six configuration control activities in order. Requirement scope has to be settled at the third of them, impact evaluation, because every later stage either uses that scope or multiplies the cost of getting it wrong:
- Identification: Someone raises a change request that names the problem and the requirements, parts or documents it touches.
- Documentation: Engineering writes the change up as a proposal carrying what the ECO will need, including affected items, proposed effectivity, inventory disposition and the actions each function owns.
- Impact evaluation: A formal change impact analysis follows the changed requirement through its linked design elements, risk items and tests to the eBOM items that realize it. The analysis then names the plants whose mBOMs carry those items, so a scope settled at this point covers every plant at once.
- Approval: Signatures come from quality, finance, supply chain and both design and manufacturing engineering, plus the customer or regulator where the industry requires it. Once the CCB or the simpler path approves it, the proposal is released as the ECO.
- Incorporation: Engineering releases the revised eBOM, and each affected plant revises its mBOM against that revision line by line under its own MCN. The released mBOM goes to ERP and MES without anyone retyping it, so production data and the ECO record agree when an auditor compares them.
- Verification: Someone confirms that every affected plant's mBOM, routing, work instructions, tooling and inventory were dealt with, then closes the change identifier used to track implementation.
Verification has to cover every plant the change reached, since each one revised its own mBOM, routing and work instructions. A close-out that checks one plant and assumes the rest leaves the others unverified.
Where Design Intent Gets Lost Along the Way
Alignment done after the fact is slow and error-prone, because someone has to walk both structures line by line when neither recorded its differences from the other as changes happened. The join between the two structures may also have no owner. Changes to the eBOM go through the change board and edits to the mBOM go through plant engineering, so a difference between the two structures belongs to neither review. A superseded revision identifier surviving in one system can lead finance to place orders against an outdated product identifier or inspection to reject newly revised parts against an older drawing. Engineers lose time as well when they work from product data that is out of date.
Checking a changed requirement's references by hand breaks down even before PLM enters the picture. Loram Maintenance of Way, Inc., which builds railway track maintenance and inspection equipment, tracked software requirements in documents before it moved off them. Its Global Standards Manager explained that "if we wanted to make a change, it was a very manual process when using Word and Excel to make sure there were no errors in documents covering any references downstream from the changed requirement or upstream in the top-level requirements." When requirements live in one tool and the product structure lives in PLM, the same walk also has to cross between the two. "Without clear traceability, the evidence linking a change to its downstream impact often doesn't exist until someone asks for it," as this guide's engineering change management chapter notes.
Teams have to settle which requirements the affected parts satisfy before the ECO is written, when the change is still a proposal. The eBOM itself stays in PLM, so each plant's later scope has to come from links among the requirement, the design elements realizing it and their verification. A change management process that captures those links at proposal time hands every plant the same answer.
Learn About Engineering Change Management
What Configuration Baselines and Variants Do to Both BOMs
Baselines fix the reference each BOM revision is measured against, and variants multiply the number of structures each baseline has to govern. Effectivity decides which units use each controlled revision. Configurable structures settle a different question, which combination of components makes a buildable product. Together these controls keep one approved design connected to the correct manufacturing structures across plants and releases.
Baselines Change Through Formal Control
A configuration baseline is "approved configuration information that establishes the characteristics of a product or service at a point in time that serves as reference for activities throughout the life cycle of the product or service," in the wording of ISO 10007:2017. So a baseline is a point-in-time reference, and it changes through formal control. The current baseline consists of the approved configuration plus its approved changes, and each approved change moves that controlled reference forward.
Programs establish three formal baselines in sequence, as identified by the superseded MIL-HDBK-61A and the Systems Engineering Body of Knowledge, each adding more detailed controlled information before production begins. Each baseline is approved at a named technical review in the mapping published by Warfighting Acquisition University (formerly the Defense Acquisition University), and the eBOM enters at the third.
| Baseline | Content | Approved at | Relationship to the BOMs |
| Functional baseline (FBL) | Performance and functional characteristics at system level, plus interoperability, interfaces and how each will be verified | System Functional Review (SFR) | Precedes any BOM |
| Allocated baseline (ABL) | Lower-level configuration items with the functional and interface characteristics assigned to each, plus design constraints and the requirements for verifying them | Preliminary Design Review (PDR) | Requirements allocated to the items the eBOM will later structure |
| Product baseline (PBL) | Detailed physical characteristics covering form, fit and function, plus the functional characteristics selected for production acceptance tests | Critical Design Review (CDR), initial | Detail design documentation |
Configuration status accounting runs alongside all three baselines and records each unit's approved configuration as changes land. In BOM terms, the eBOM revision approved at CDR is the physical description inside the PBL. Manufacturing engineering establishes the mBOM baseline from that revision, and every ECO approved afterward moves both.
Effectivity by Serial, Lot and Date
The plant uses the effectivity in the change package to decide which units get the change, in both the eBOM and the mBOM. Written in 2001, MIL-HDBK-61A expresses part effectivity as the serial-number range of the end items that receive the part. Date, lot, block and contract-year effectivity all work, provided each one resolves back to the specific serial-numbered units that will carry the part.
Effectivity can be managed in PLM or passed downstream to ERP as a date or a lot or serial-number range. Revision effectivity applies the same way to every use of a part. Occurrence effectivity is set use by use, and mixing the two on one product complicates the configuration logic. For the systems engineer, effectivity converts a requirement change into a statement about which fielded units still meet the old requirement and which meet the new one.
150% BOMs and Variant Reuse
A 150% BOM holds every option a product line offers, and configuration rules filter it down to the 100% BOM a given order builds. The 150% eBOM can feed several configured mBOMs through variant rules, each 100% mBOM carrying the effectivity and variant values of one buildable configuration. Without those variant rules, every new copy of a structure is another place engineering and manufacturing data can disagree.
A variant's requirement set is filtered from a shared requirement set in the same way, and the shared requirements are worth reusing across releases. Eneon, which builds configurable battery energy storage systems, manages its products with 75% shared and 25% customer-specific requirements. Shared requirements still change, and a change to one reaches every configuration that reuses it. A rewritten shared safety requirement has to be re-verified in each of those configurations, and the customer-specific quarter carries its own verification plus the integration checks each new configuration needs.
Why Regulated Programs Now Track a Software Bill of Materials Alongside Both
Regulated programs track an SBOM because a software component version is a configuration item like any part, and the SBOM makes a version change as visible as an ECO makes a part change. An SBOM is "a formal record containing the details and supply chain relationships of various components used in building software," in the 2021 minimum elements from the National Telecommunications and Information Administration (NTIA), which the 2026 guidance from the Cybersecurity and Infrastructure Security Agency (CISA) has since replaced. The record lists proprietary, third-party and open-source components with their versions and licenses, and known vulnerabilities are tracked in separate data linked to the SBOM. Hardware and service BOMs omit this software inventory. Because "sBOM" can also mean the service BOM used for spares and field maintenance, a regulated program has to say which artifact a document means.
Four instruments now shape SBOM content and the cybersecurity controls around it, and the table lists each with its issuing body and current status. CISA's minimum elements, FDA's premarket guidance and the European Union (EU) regulation address the SBOM directly. The vehicle regulation in the last row requires a cyber security management system without naming an SBOM.
| Instrument | Issuing body | Status |
| 2026 Minimum Elements for a Software Bill of Materials | CISA with the National Security Agency, the Federal Bureau of Investigation and international partners | Replaced the NTIA 2021 minimum elements and added elements including component hash, component license, SBOM author signature, SBOM tool name, data format and generation context. |
| Cybersecurity in Medical Devices: Quality Management System Considerations and Content of Premarket Submissions | FDA | Final guidance, February 2026. Includes FDA’s recommendations for Section 524B cyber devices. |
| Cyber Resilience Act (CRA), Regulation (EU) 2024/2847 | European Parliament and Council of the EU | Article 14 vulnerability and incident reporting has been in effect since September 11, 2026. The SBOM requirement and the regulation’s other product obligations are effective December 11, 2027. |
| United Nations (UN) Regulation No. 155 | UN Economic Commission for Europe, through its World Forum for Harmonization of Vehicle Regulations (WP.29) | Mandatory in the EU for new vehicle types from July 2022 and for all new vehicles produced from July 2024. Requires a cyber security management system, including how it manages supplier dependencies, without naming an SBOM. |
Widely used machine-readable SBOM formats include System Package Data Exchange (SPDX) and CycloneDX. Beyond software, CycloneDX also covers hardware, machine learning models, cryptography and software-as-a-service. A program that already keeps the eBOM and mBOM in step can treat the SBOM as a third derived structure. Each component version change in it then takes an effectivity and a disposition decision, as a part change under a hardware ECO does.
How Jama Connect Supports eBOM and mBOM Alignment
Jama Connect® is a web-based requirements management and traceability platform, and it works alongside the eBOM, mBOM and SBOM, which stay in their systems of record. Its before-change impact analysis shows every downstream item linked to a requirement, across one, two, three or more degrees of separation, so the design elements, risk items and tests a proposed change touches are in view at the impact evaluation stage, before approval turns the proposal into an ECO. The Jama Connect Traceability Information Model (TIM) flags any requirement that is missing a required design element or test, and when a linked requirement changes, suspect links flag every downstream design element, risk item and test case for assessment. Engineers either update each flagged item or clear the suspect link, which leaves a record of who cleared each effect and catches the requirements side of an ECO that stops at the eBOM. Whether that ECO ever reaches the mBOM is still recorded in PLM, ERP or MES.
Pre-built integrations across the application lifecycle management (ALM) and PLM toolchain, plus an open Representational State Transfer (REST) application programming interface (API), connect Jama Connect with the tools around it. For baselines and variants, Baseline Compare shows added and removed items, modified fields and new or broken relationships between two Jama Connect baselines, so it captures the requirement-side change an approved ECO makes, and the PBL itself, eBOM included, stays in PLM. Categories filter requirements by variant, so the shared and variant-specific portions of a 150% requirement set can be reviewed separately, and Reuse and Sync can push updates made in a master set of shared requirements out to the derivative projects that reuse them. The hand-keyed first mBOM, uncoordinated plant edits, the missing parent revision, the unrecorded regrouping and each plant's mBOM, routing and work-instruction updates all live in PLM, ERP or MES records that Jama Connect does not hold.
Scoping a Requirement Change Before It Splits Into Manufacturing Change Notices
Requirement scope belongs before the ECN divides, because after the split every question about which requirements the change touches has to be answered again for each MCN. Each of those answers comes from people at different plants working from different structures. With the scope on record first, an auditor reviewing a plant substitution can see which requirements and verification the affected design element carries, and the mBOM's own record then has to explain only why the part was substituted. When the EU CRA's SBOM obligation arrives on December 11, 2027, that single pre-split pass will cover a software structure as well.
Jama Connect supports this workflow by keeping each requirement linked to the design elements and tests that realize and verify it, so scope is settled once, before the split. A free 30-day trial is long enough to scope one multi-plant engineering change from its linked requirements before its ECN splits.
Frequently Asked Questions About eBOM vs mBOM
Can an mBOM include parts that aren’t in the eBOM?
An mBOM can carry extra lines when they support production without changing the approved design, and the reverse case is the one to watch. Dropping a designed part from the mBOM is a defect, because a part that never reaches the build breaks product traceability in regulated industries for every requirement allocated to it. Each line that appears in only one structure needs an owner and a status, and any line without a recorded production reason should be investigated.
How is the mBOM different from the as-built record?
The mBOM is the manufacturing plan, and the as-built record captures what each unit consumed, down to the lot and serial number that scope a defect investigation or field action. In medical devices that record is the medical device or batch record under ISO 13485 Clause 7.5.1, which the Quality System Regulation called the device history record (DHR) until the QMSR took effect. Defense programs rely on configuration status accounting, which records the as-built configuration of each serial-numbered unit. When consumption departs from the plan under an approved deviation, both records are kept and unit history stays outside the mBOM, so end-to-end traceability still reaches each delivered unit.
When does a product need separate eBOM and mBOM structures?
Separate structures become necessary once manufacturing needs data the design structure shouldn't carry, such as station quantities, process-only materials, plant alternates or effectivity rules that would clutter engineering review. Phase-in is the case even small teams hit, because old and new parts overlap under different effectivities and the two structures have to diverge for that period anyway. Whatever the product size, keep requirement-to-eBOM links current and run a change impact analysis before each phase-in, which in Jama Connect covers every item linked to the changed requirement.
Is a software BOM the same thing as a service BOM?
A service BOM supports maintenance of a fielded product, and an SBOM inventories its software components, so the two answer different questions about the same product. Their change triggers differ as well, since a software component update calls for cybersecurity and vulnerability review and a service BOM revision supports field replacement and maintenance planning. Programs should give each its own document identifier, approval path and owner. Controlled documents should spell out "service BOM" and reserve "SBOM" for the inventory of software components that the EU CRA and FDA Section 524B refer to.
If I want to learn more about eBOM vs mBOM, what else should I read?
Medical device teams can see how the records that carry a design into production changed in DHF vs DMR vs DHR. For how product data stays connected from requirements through manufacturing, read about the digital thread.