What Are Design Controls? A Guide to the Process and Its Elements

Since February 2, 2026, the former design controls provision has read “[Reserved].” That day the Quality Management System Regulation (QMSR) took effect and moved the requirement to section 820.10(c) of Title 21 of the Code of Federal Regulations (CFR), which incorporates International Organization for Standardization (ISO) 13485:2016 Clause 7.3 by reference. Its paragraph heading now reads “Design and development,” and the U.S. Food and Drug Administration (FDA) no longer defines the design history file (DHF), the device master record (DMR) or the device history record (DHR).

FDA investigators stopped using the Quality System Inspection Technique (QSIT) on the same date and now follow a compliance program that organizes an inspection around six quality management system areas and treats Design and Development as one of them. Each element in Clause 7.3 produces a record, and an auditor reads those records as one chain from input to verified output, so a design that is complete element by element can still fail when the links between them were never kept. Two warning letters show where the records behind that chain go missing, one citing an approved change closed out without records of the necessary actions and another a design validation with no rationale for its sample size. This guide covers who the design and development requirements apply to, what each of the nine elements demands and how auditors trace the records those elements produce.

Where Design Controls Sit Under the QMSR

Under the QMSR, medical device design controls apply by device class. The text of 21 CFR 820.10(c) states that manufacturers of Class II devices, Class III devices and the Class I devices it lists “must comply with the requirements in Design and Development, Clause 7.3 and its Subclauses in ISO 13485.” Medical device design controls is the name the former Quality System Regulation (QSR) gave the design and development process, and the one the industry still uses. The QMSR incorporates ISO 13485:2016(E), third edition, dated March 1, 2016, which gives teams a stable regulatory target.

FDA and ISO 13485 harmonization also means an FDA investigator and an ISO 13485 auditor now read the same clause text, which removes a translation step that used to sit between a U.S. inspection and a notified body audit. Because the elements map one-to-one onto the ISO design and development sequence, a procedure still indexed on the old paragraph letters can point each former paragraph, from planning through the DHF, at its Clause 7.3 counterpart.

Former QSR design control element (Reserved since February 2, 2026) ISO 13485:2016 element
Design and development planning Design and development planning
Design input Design and development inputs
Design output Design and development outputs
Design review Design and development review
Design verification Design and development verification
Design validation Design and development validation
Design transfer Design and development transfer
Design changes Control of design and development changes
DHF Design and development file

DHF vs DMR vs DHR

The Nine Elements of Design and Development Under ISO 13485 Clause 7.3

ISO 13485 Clause 7.3 requires documented procedures for design and development, and each element carries a “shall” and a record an auditor can ask to see. Warning letters issued under both the QSR and the QMSR cite missing records under individual elements, and the letters linked below show which record each citation found missing.

Design and Development Planning (7.3.2)

Clause 7.3.2 requires the plan to document the method of traceability. The same subclause asks the plan to set out the design and development stages, the reviews needed at each stage, the verification, validation and transfer activities, responsibilities and authorities, and the resources needed, including personnel competence. A phase-gate schedule with milestones satisfies the stages and reviews items and says nothing about how outputs will be traced back to inputs, which leaves a listed requirement unaddressed.

Traceability matrices connecting design and development inputs to outputs are one practical way to meet that need and give a reviewer a clear starting point. Beginning design work with no procedures and no design and development plan fails the planning requirement outright.

Design and Development Inputs (7.3.3)

Clause 7.3.3 requires inputs that can be verified or validated, and that matters because every later record points back to them. Inputs “must be complete, unambiguous, and not conflict,” according to FDA’s QMSR training material. Clause 7.3.3 requires five categories, one of them (information from previous similar designs) applicable as appropriate:

  • Functional, performance, usability and safety requirements: The requirements state what the device must meet in use, including what the user has to be able to do with it and what must not happen when they do.
  • Applicable regulatory requirements and standards: Regulations and standards that apply to the device in each intended market enter the input set through this category before later compliance checks.
  • Applicable outputs of risk management: Risk controls identified through ISO 14971 analysis enter design as requirements the design must implement, and FDA’s QMSR training frames inputs as accounting “for pertinent risk management outputs.” If the risk management file lists a control and no input carries it, the input set is incomplete before design work begins.
  • Information from previous similar designs: Information from previous similar designs captures lessons from earlier devices in the family, such as field data and prior verification results.
  • Other essential requirements: Any other requirement essential to the design and development of the product and its processes enters the input set here.

A requirement such as “the infusion pump shall alarm promptly on occlusion” fails the verifiability test because no protocol can be written with a pass threshold against “promptly.” The alarm-latency figure the hardware team assumes can then differ from the one the software team builds to, and the difference may not surface until integration. For software-containing, connected devices, threat modeling belongs inside the design and development process under FDA cybersecurity guidance, so security requirements belong in this input set as well. Turning a user need into a testable statement is its own discipline, and the guide to translating user needs into design inputs walks through it.

Design and Development Outputs (7.3.4)

Outputs shall be provided in a form that allows verification and validation to be performed, which means a specification with a tolerance rather than a description of intent. Under Clause 7.3.4, outputs have to meet the input requirements, give purchasing, manufacturing and servicing the information they need, contain or reference acceptance criteria and specify the characteristics essential to safe use. Each output has to be checkable against the input it satisfies. Manufacturers use approved outputs at design release as the record for this subclause.

Approved outputs also become the starting material for the manufacturing record. The final design output, maintained or referenced in the design and development file, is the basis or starting point for the medical device file under Clause 4.2.3, according to the QMSR preamble. Under the QMSR, FDA no longer uses the term DMR as a defined record type. Many of the underlying elements previously associated with the DMR are addressed through ISO 13485 requirements, including the medical device file in Clause 4.2.3. An output that isn’t in a controlled, versioned form at release becomes a problem twice, once at verification and again when production tries to build from it.

Design and Development Review (7.3.5)

Reviews happen at the stages the plan named, and Clause 7.3.5 requires participants to include representatives of the functions concerned with the stage under review. A software-only review of a stage that changed a hardware interface is therefore a finding in itself. The mandatory record is the results of the review together with any necessary actions. A record that lists attendees and a “passed” outcome without the actions raised and their disposition is incomplete under the current text.

Each stage review should also cover risk management evidence. Medical Device Single Audit Program (MDSAP) auditors confirm that risk acceptability criteria are established and met throughout design and development, and that any residual risk is evaluated and, where appropriate, communicated, according to the MDSAP audit approach.

Teams that record reviews electronically and rely on the electronic record must apply 21 CFR Part 11 to the record and its signatures. Enforcement discretion applies to the validation, audit trail and record copying requirements under FDA’s 2003 Part 11 guidance, but the predicate rule, here ISO 13485 as incorporated, still requires the record to exist and be controlled.

Design and Development Verification (7.3.6)

Verification answers whether the outputs of a design activity met the inputs for that activity, or “Did I make the product right?” as an FDA presentation on its human factors guidance put it in 2012. Clause 7.3.6 requires verification per planned arrangements and records of the results and any necessary actions. Verification plans have to document methods, acceptance criteria and, as appropriate, statistical techniques with a rationale for sample size, and any connections or interfaces with other devices or systems have to be confirmed. The work can happen at every stage and level of design throughout development.

Verification records fail visibly when they omit the sample size rationale. An October 2025 FDA warning letter cited missing sample-size rationales for both design verification and design validation, each a repeat violation from a July 2016 inspection. Although the 2025 inspection behind that letter predated the QMSR effective date, the obligations it describes carry straight into Clause 7.3.6. The absence of a verification procedure leaves the verification requirement unaddressed.

Design and Development Validation (7.3.7)

Validation asks “Did I make the right product?” and tests the finished design against the requirements for its specified application or intended use. Clause 7.3.7 requires validation to follow documented plans that set out methods, acceptance criteria and, as appropriate, statistical techniques with a rationale for the sample size. The clause also requires clinical evaluations or performance evaluations as part of validation, in line with applicable regulatory requirements, and validation must be complete before the product is released.

Validation has to run on representative product, and FDA’s QMSR training spells out what that means. Representative product means initial production units or their equivalent, and the rationale for the choice must be recorded. Under the QSR, FDA cited manufacturers when they did not perform validation under defined operating conditions on initial production units.

Software validation sits inside design validation and is “a part of the design validation for a finished device,” according to FDA’s General Principles of Software Validation. Usability validation typically follows International Electrotechnical Commission (IEC) 62366-1, which FDA recognizes as a consensus standard.

Design and Development Transfer (7.3.8)

ISO 13485:2016 gives transfer its own subclause, and manufacturers must document procedures for transferring outputs to manufacturing. Under Clause 7.3.8, transfer procedures have to show that each output was checked as suitable for manufacturing before it was released as a production specification, and that production capability can meet product requirements. Manufacturers shall record the results and conclusions of the transfer, and an auditor asks for that record. “Determine if the design was correctly transferred to production” is the objective mapped to this subclause in MDSAP audit task 16.

Production that starts on the strength of an email saying the drawings are done, with no recorded confirmation that the outputs can be produced at scale, is a nonconformance against the transfer subclause. Process validation can also begin at the same handoff.

Control of Design and Development Changes (7.3.9)

Under Clause 7.3.9, change control requires documented procedures, a determination of each change’s significance to function, performance, usability, safety and regulatory requirements, and review, verification or validation as appropriate, with approval before implementation. The change evaluation has to cover the change’s effect on the outputs of risk management, on product realization processes, on constituent parts and the product, and on units still in process or already delivered. Records of each change, its review and any necessary actions have to be kept.

Inadequate review, verification, validation and approval before implementation have resulted in FDA citations under Clause 7.3.9. An August 2026 letter cited multiple software changes approved, implemented and closed without records showing that the changes were correctly, completely or safely implemented. Design changes drew warning-letter citations under the QSR as well.

Whether the device is already on the market changes the paperwork as well. A change that could significantly affect the safety or effectiveness of a device cleared through 510(k), or a major change to its intended use, requires a new 510(k), with the comparison made against the device in its most recently cleared 510(k). For a device approved through Premarket Approval (PMA), a PMA supplement, reviewed and approved by FDA, is required before a change affecting safety or effectiveness is made, unless an alternate submission type or an exemption applies.

The Design and Development File (7.3.10)

FDA itself maps the former DHF to Clause 7.3.10. Clause 7.3.10 states that manufacturers “shall maintain a design and development file for each medical device type or medical device family,” and the file “shall include or reference records generated to demonstrate conformity to the requirements for design and development and records for design and development changes.” “Include or reference” makes the file a container with pointers, so records of changes can live in change control and still be part of the file.

The file provides “documented evidence that design activities were planned, executed, reviewed, and controlled throughout the product lifecycle, and that the final design meets both user needs and regulatory requirements,” according to FDA’s January 2026 town hall material. Under the QSR, the file was specifically required in its own subsection, 21 CFR 820.30(j), and had to contain or reference records demonstrating that the design was developed in accordance with the approved design plan and applicable requirements. The QMSR treats it as one of the ISO 13485 records, and an inspector checks whether it includes or references everything the other eight elements generated.

DHF is still a common term in procedures and conversation, and FDA staff said at a January 2026 town hall that the agency does not expect firms to scrub existing design files of QSR-era terms such as “design history file.” The regulation “eliminated terms associated with these specific record types,” in the preamble’s words, because ISO 13485 requires the same elements through its document and design requirements. What the DHF held under the QSR is covered in the Design History File chapter. The guide to the DHF, DMR and DHR covers how the DHF related to the DMR and the DHR.

Verification vs. Validation Evidence Compared

Verification evidence shows each output met its input at the stage it was produced, and validation evidence shows the finished design meets user needs on representative product, which is why the two sets of records differ on most rows below. The two still get confused in submissions, so the table sets them side by side.

Dimension Verification (7.3.6) Validation (7.3.7)
Timing Throughout development, at every stage and level Before release, on the final design
Units tested Design outputs at any stage Initial production units, batches or documented equivalents
Conditions As the test method requires Representative product, against the specified application or intended use
Users involved Not required Representative intended users for usability validation
Statistical rationale Methods, acceptance criteria and, as appropriate, statistical techniques with a rationale for sample size Same as verification
Software Unit, integration and system testing under IEC 62304 Software validation as part of design validation
Usability Performance criteria met Summative evaluation under IEC 62366-1

Under IEC 62304, software lifecycle activities run inside the design and development process. Software validation is the “confirmation by examination and provision of objective evidence that software specifications conform to user needs and intended uses, and that the particular requirements implemented through software can be consistently fulfilled,” according to FDA’s software validation guidance.

The verification and validation split applies to usability evidence too. Usability validation “demonstrates and provides evidence that a medical device, as designed, can be used safely and effectively” by people representative of the intended users, under expected use conditions, for essential and critical tasks, according to a 2012 FDA presentation on its human factors guidance. The root causes of all use errors and problems seen in validation testing should be considered against the associated risks, according to FDA’s human factors guidance, so a summative study that reports a pass rate without analyzing each use error falls short.

Where ISO 14971 Risk Management Enters Design Controls

Risk management under ISO 14971:2019, which FDA recognizes as a consensus standard, enters the design and development process at three points, the inputs, the verification and validation records and every change evaluation. Under the former QSR, risk appeared once in the design control text, as risk analysis within design validation, where appropriate. ISO 13485:2016 carries risk management and risk-based decisions into multiple clauses, including product realization planning and design and development, as FDA’s QMSR training explains.

Verifying Risk Controls Inside Design Verification and Validation

Teams must verify the implementation of each risk control measure and record that verification in the risk management file, as ISO 14971:2019 Clause 7.2 requires. Implementation verification can be performed as part of design and development verification under the clause’s first note. Its second note allows verification of effectiveness to be performed as part of design and development validation, including testing with users. An auditor should therefore be able to reach the same test record through both the design verification record and the risk management file. Design validation can provide evidence that risk controls are effective under intended-use conditions, while residual-risk acceptability is evaluated through the ISO 14971 risk-management process.

The expectation predates the QMSR, since Global Harmonization Task Force (GHTF) guidance already called for design and development verification to generate objective evidence that identified risks were addressed and risk control measures were implemented as necessary. A verification protocol that never names which risk control it exercises produces evidence the risk file can’t point to. The August 2026 warning letter shows what an unverified control looks like at inspection, with the risk control verification entries for software, sterilization, storage, packaging and exudate management all marked “In Progress” and the controls not yet implemented and verified.

Re-Evaluating Risk After a Design Change

A change to a design input can invalidate a hazard analysis that was correct when written, which is why the change-control subclause requires change evaluation to cover the outputs of risk management. Auditors are directed to verify that “any new risks associated with the design change have been identified and mitigated to the extent practical” by MDSAP audit task 13.

When the hazard analysis lives in a spreadsheet and the requirements live in a document set, a requirement changed in March leaves a risk assessment from the previous year looking current on paper. Often the disconnect stays hidden until an auditor asks for the change record. The cost lands on impact analysis, where a team has to find every risk record a change touches before approving it. Össur, which builds prosthetics, bracing and bionic limbs and works to ISO 14971 and ISO 13485, reports impact analysis review in five minutes against hours. On what that work demands without connected records, its Director of R&D Bionic Solutions said, “If you have five or six developers that are working concurrently, just making sure that your traceability doesn’t develop gaps is a full-time job.”

FMEA Framework for Medical Device Development

Why Auditors Read Design Controls as a Traceability Chain

Auditors read design controls as a traceability chain because no Clause 7.3 record proves conformity on its own. Since FDA replaced QSIT with its current compliance program, investigators also use the firm’s risk management documentation to decide what to examine. For audit preparation, teams can mirror that approach by checking the chain in both directions before an investigator arrives.

The chain runs through five record sets:

  • Requirements entering design: The functional, performance, usability and safety requirements the device must meet for its intended use, including the risk controls carried in from the hazard analysis.
  • Outputs expressed as specifications: The device description, drawings, specifications and bill of materials belong here, and each one should be traceable to the input it satisfies.
  • Verification plan with its summary report: Supporting data should accompany these records, along with traceability back to the inputs each test exercises.
  • Validation evidence, plan and summary report: Traceability to the user needs and intended use covered by each study should appear with the supporting data.
  • The risk management file: Hazards, controls and the verification of each control are recorded in this file, which should point to the design and test records that implemented and verified the control.

Notified bodies under the European Union Medical Device Regulation (EU MDR) ask for the same chain in a different vocabulary. They expect a design control input/output matrix, with test data critically analyzed and linked to specific General Safety and Performance Requirements (GSPRs) and related risk controls, according to Team-NB’s best practice guidance on EU MDR technical documentation. A matrix assembled the month before an audit from documents that were never linked while the design moved may disagree with the file it summarizes because the team inferred the links after the fact. The traceability method defined during planning therefore has to be a working mechanism that produces the deliverable. Fragmented quality management, product lifecycle management, enterprise resource planning and shared-file environments make the full chain difficult to demonstrate.

Checking the completed chain before an audit finds the missing links while they are still a correction, before they contribute to a recall, inspection finding or submission delay. A connected chain also makes it easier to locate every affected record when a requirement, risk control or test changes.

How Jama Connect Supports Design Controls

Jama Connect®, a web-based requirements management and traceability platform for complex, regulated product development, carries a medical device framework with pre-built workflows for design inputs, design outputs, design verification, design validation and design transfer, aligned to ISO 13485 Clause 7.3. Its Traceability Information Model (TIM) defines the input-to-output-to-test relationships the plan’s traceability method calls for. Where a design output has no linked verification test, or any other required link does not exist yet, the TIM flags it, and Live Trace Explorer™ reports coverage for the whole project. Jama Intelligence, an add-on for Jama Connect Cloud, scores requirement text against 30 of the 40 International Council on Systems Engineering (INCOSE) rules. Stage reviews run in Review Center, whose electronic signatures and audit trail support customers’ 21 CFR Part 11 compliance processes.

For change control, suspect links and impact analysis show which outputs, tests and risk records a change evaluation has to cover. Hazard analysis and Failure Mode and Effects Analysis (FMEA) records can point to the same test record used to verify the requirement that implements a risk control. Pre-built risk analysis reports come with the medical framework, so a team reviewing those hazard and FMEA links starts from a pre-built report layout, with no template to write first. For the design and development file, export templates generate DHF and EU MDR technical documentation exports from the working records.

Keeping the Design Control Chain Connected Between Audits

Design and development requirements under the QMSR are not intended to be retroactive, so a design and development file closed before February 2, 2026, stays as it was filed. The pressure arrives with the first design change after that date, because its Clause 7.3.9 evaluation has to reach into the legacy records and the new Clause 7.3 records at once, and a team that links the two sets at that change avoids rebuilding the chain for every later submission.

A traceability matrix export in Jama Connect supports this workflow because it generates the full chain from user needs through verification out of the project’s live links, and the matrix a notified body receives is then the one the team works in. Your next design review is a natural point to start a free 30-day trial and watch that chain hold on a current project.

Explore Medical Device Solutions

Start Free Trial

Frequently Asked Questions About Design Controls

Do design controls apply to Class I medical devices?

Some do, because the design and development requirements in 21 CFR 820.10(c), still called design controls across the industry, cover only the Class I devices that paragraph names. The covered group includes devices automated with computer software and five listed device types, namely the catheter tracheobronchial suction, the non-powdered surgeon’s glove, the protective restraint, the manual radionuclide applicator system and the radionuclide teletherapy source. Every other Class I device sits outside Clause 7.3, while all Class II and Class III devices are inside it.

Is FDA’s 1997 design control guidance still valid?

No, FDA withdrew the 1997 Design Control Guidance for Medical Device Manufacturers on February 2, 2026, the day the QMSR took effect, and lists it among its withdrawn guidance documents. Guidance issued before that date, such as the General Principles of Software Validation, now carries a notice that FDA “encourages manufacturers to review the current QMSR to ensure compliance with the relevant regulatory requirements.” The requirement itself is the Clause 7.3 text that the QMSR incorporates through 21 CFR 820.10(c).

How long must design and development records be kept?

Under EU MDR, the technical documentation and the EU declaration of conformity stay available to competent authorities for at least 10 years after the last covered device is placed on the market, and for at least 15 years for implantable devices. In the U.S., the retention period comes from the record-control clause the QMSR incorporates, ISO 13485 Clause 4.2.5, and 21 CFR 820.35 adds record content requirements on top of that clause without setting a period of its own. Medical device reporting event files, a separate obligation from the design and development file, are kept for two years or the expected life of the device, whichever is longer. Across these retention periods, Jama Connect maintains a version history on every item that shows who changed each field and when.

If I want to learn more about design controls, what else should I read?

The wider process that design controls sit inside is covered in our guide to medical device requirements management. For validating the production and quality system software that holds design records, read about computer software assurance.

This article was authored by Tom Rish and published on October 30, 2026.

See Jama Connect in Action!

Our Jama Connect experts are ready to guide you through a personalized demo, answer your questions, and show you how Jama Connect can help you identify risks, improve cross-team collaboration, and drive faster time to market.