Disciplined software organizations collect a focused set of metrics about each of their projects. These metrics provide insight into the size of the product; the effort, time, and money that the project or individual tasks consumed; the project status; and the product’s quality. Because requirements are an essential project component, you should measure several aspects of your requirements engineering activities. This two-part series, adapted from my book More about Software Requirements, describes several meaningful metrics related to requirements activities on your projects. Enjoy these free requirements management resources.

Product Size

The most fundamental metric is the number of requirements in a body of work. Your project might represent requirements by using a mix of use cases, functional requirements, user stories, feature descriptions, event-response tables, and analysis models. However, the team ultimately implements functional requirements, descriptions of how the system should behave under specific conditions.

Begin your requirements measurement by simply counting the individual functional requirements that are allocated to the baseline for a given product release or development iteration. If different team members can’t count the requirements and get the same answer, you have to wonder what other sorts of ambiguities and misunderstandings they’ll experience. Knowing how many requirements are going into a release will help you judge how the team is progressing toward completion because you can monitor the backlog of work remaining to be done. If you don’t know how many requirements you need to work on, how will you know when you’re done?

Of course, not all functional requirements will consume the same implementation and testing effort. If you’re going to count functional requirements as an indicator of system size, your analysts will need to write them at a consistent level of granularity. One guideline is to decompose high-level requirements until the child requirements are all individually testable. That is, a tester can design a few logically related tests to verify whether a requirement was correctly implemented. Count the total number of child requirements, because those are what developers will implement and testers will test. Alternative requirements sizing techniques include use case points and story points. All of these methods involve estimating the relative effort to implement a defined chunk of functionality.

Functional requirements aren’t the whole story, of course. Stringent nonfunctional requirements can consume considerable design and implementation effort. Some functionality is derived from specified nonfunctional requirements, such as security requirements, so those would be incorporated appropriately into the functional requirement size estimate. But not all nonfunctional requirements will be reflected in this size estimate. Be sure to consider the impact of nonfunctional requirements upon your effort estimate. Consider the following situations:

  • If the user must have multiple ways to access specific functions to improve usability, it will take more development effort than if only one access mechanism is needed.
  • Imposed design and implementation constraints, such as multiple external interfaces to achieve compatibility with an existing operating environment, can lead to a lot of interface work even though you aren’t providing additional new product functionality.
  • Strict performance requirements might demand extensive algorithm and database design work to optimize response times.
  • Rigorous availability and reliability requirements can imply significant work to build in failover and data recovery mechanisms, as well as having implications for the system architecture you select.

You’ll also find it informative to track the growth in requirements as a function of time, no matter what requirements size metric you use. One of my clients found that their projects typically grew in size by about twenty-five percent before delivery. Amazingly, they also ran about twenty-five percent over the planned schedule on most of their projects. Coincidence? I think not.

Requirements Quality

Consider collecting some data regarding the quality of your requirements. Inspections of requirements specifications are a good source of this information. Count the requirements defects you discover and classify them into various categories: missing requirements, erroneous requirements, unnecessary requirements, incompleteness, ambiguities, and so forth. Use defect type frequencies and root-cause analysis to tune up your requirements processes so the team makes fewer of these types of errors in the future. For instance, if you find that missing requirements are a common problem, your elicitation approaches need some adjustments. Perhaps your business analysts aren’t asking enough questions or the right questions, or maybe you need to engage more appropriate user representatives in the requirements development process.

If the team members don’t think they have time to inspect all their requirements documentation, try inspecting a sample of just a few pages. Then calculate the average defect density—the number of defects found per specification page—for the sample. Assuming that the sample was representative of the entire document (a big assumption), you can multiply the number of uninspected pages by this defect density to estimate the number of undiscovered defects that could still lurk in the specification. Less experienced inspectors might discover only, say, half the defects that actually are present, so use this estimated number of undiscovered defects as a lower bound. Inspection sampling can let you assess the document’s quality so that you can determine whether it’s cost effective to inspect the rest of the requirements specification. The answer will almost certainly be yes.

Also, keep records of requirements defects that are identified after the requirements are baselined, such as requirements-related problems discovered during design, coding, and testing. These represent errors that leaked through your quality control filters during requirements development. Calculate the percentage of the total number of requirements errors that the team caught at the requirements stage. Removing requirements defects early is far cheaper than correcting them after the team has already designed, coded, and tested the wrong requirements.

Two informative metrics to calculate from inspection data are efficiency and effectiveness. Efficiency refers to the average number of defects discovered per labor hour of inspection effort. Effectiveness refers to the percentage of the defects originally present in a work product that was discovered by inspection. Effectiveness will tell you how well your inspections (or other requirements quality techniques) are working. Efficiency will tell you what it costs you, on average, to discover a defect through inspection. You can compare that cost with the cost of dealing with requirements defects found later in the project or after delivery to judge whether improving the quality of your requirements is cost effective.

The second article in this series will address metrics related to requirements status, change requests, and the effort expended on requirements development and management activities.

Also read Measuring Requirements: Status and Requests for Changes.

Jama Software has partnered with Karl Wiegers to share licensed content from his books and articles on our web site via a series of blog posts, whitepapers and webinars.  Karl Wiegers is an independent consultant and not an employee of Jama.  He can be reached at http://www.processimpact.com.  Enjoy these free requirements management resources.

This article continues the exploration of requirements-related metrics that I began in Part 1, which looked at measuring product size and requirements quality.

Requirements Status

Track the status of each requirement over time to monitor overall project status, perhaps defining a requirement attribute to store this information. Status tracking can help you avoid the pervasive “ninety percent done” problem of software project tracking. Each requirement will have one of the following statuses at any time.

  • Proposed (someone suggested it)
  • Approved (it was allocated to a baseline)
  • Implemented (the code was designed, written, and unit tested)
  • Verified (the requirement passed its tests after integration into the product)
  • Deferred (the requirement will be implemented in a future release)
  • Deleted (you decided not to implement it at all)
  • Rejected (the idea was never approved)

Other status options are possible, of course. Some organizations use a status of “Reviewed” because they want to confirm that a requirement is of high quality before allocating it to a baseline. Other organizations use “Delivered to Customer” to indicate that a requirement has actually been released.

When you ask a developer how he is coming along, he might say, “Of the eighty-seven requirements allocated to this subsystem, sixty-one of them are verified, nine are implemented but not yet verified, and seventeen aren’t yet completely implemented.” There’s a good chance that not all these requirements are the same size, will consume the same amount of implementation effort, or will deliver the same customer value. If I were a project manager, though, I’d feel that we had a good handle on the size of that subsystem and how close we were to completion. This is far more informative than, “I’m about ninety percent done. Lookin’ good!”

Requests for Changes

Much of requirements management involves handling requirement additions, modifications, and deletions. Therefore, track the status and impact of your requirements change requests. The data you collect should let your team answer questions such as the following:

  • How many change requests were submitted in a given time period?
  • How many of these requests are open, and how many are closed?
  • How many requests were approved, and how many were rejected?
  • How much effort did the team spend implementing each approved change?
  • How long have the requests been open on average?
  • On average, how many individual requirements or other artifacts are affected by each submitted change request?

Monitor how many changes are incorporated throughout development after you baselined the requirements for a specific release. Note that a single change request potentially can affect multiple requirements of different levels and types (user requirements, functional requirements, nonfunctional requirements). To calculate requirements volatility over a given time period, divide the number of changes by the total number of requirements at the beginning of the period (for example, at the time a baseline was defined):

The intent is not to try to eliminate requirements volatility. There are often good reasons to change requirements. However, we need to ensure that the project can manage the degree of requirements changes and still meet its commitments. Changes become more expensive as the product nears completion, and a sustained high level of approved change requests makes it difficult to know when you can ship the product. Most projects should become more resistant to making changes as development progresses, meaning the trend of accepted changes should approach zero as you near the planned completion date for a given release. An iterative development approach gives the team multiple opportunities to incorporate changes into subsequent iterations, while still keeping each iteration on schedule.

If you receive many change requests, that suggests that elicitation overlooked many requirements or that new ideas keep coming in as the project drags along month after month. Record where the change requests come from: marketing, users, sales, management, developers, and so on. The change request origins will tell you who to work with to reduce the number of overlooked, modified, and misunderstood requirements.

Change requests that remain unresolved for a long time suggest that your change management process isn’t working well. I once visited a company where a manager wryly admitted that they had enhancement requests that were several years old and still pending. This team should allocate certain of their open requests to specific planned maintenance releases and convert other long-term deferred change requests to a status of rejected. This would help the project manager focus the team’s energy on the most important and most urgent items in the change backlog.

Effort

Finally, I recommend that you  record the time your team spends on requirements engineering activities. These activities include both requirements development (getting and writing good requirements) and requirements management (dealing with change, tracking status, recording traceability data, and so on).

I’m frequently asked how much time and effort a project should allocate to these functions. The answer depends enormously on the type and size of project, the developing team and organization, and the application domain. If you track your own team’s investment in these critical project activities, you can better estimate how much effort to plan for future projects.

Suppose that on one previous project, your team expended ten percent of its effort on requirements activities. In retrospect, you conclude that the requirements were too poorly defined and the project would have benefited from additional investment in developing quality requirements. The next time your team tackles a similar project, the project manager would be wise to allocate more than ten percent of the total project effort to the requirements work.

As you accumulate data, correlate the project development effort with some measure of product size. The documented requirements should give you an indication of size. You could correlate effort with the count of individually testable requirements, use case points, function points, or something else that is proportional to product size. As Figure 1 illustrates, such correlations provide a measure of your development team’s productivity, which will help you estimate and scope individual release contents. If you collect some product size data and track the corresponding implementation effort, you’ll be in a better position to create meaningful estimates for similar projects in the future.

Figure 1. Correlating requirements size with project effort gives a measure of team productivity. Each point represents a separate project.

Some people are afraid that launching a software measurement effort will consume too much time, time they feel should be spent doing “real work.” My experience, though, is that a sensible and focused metrics program doesn’t take much time or effort at all. It’s mostly a matter of developing a simple infrastructure for collecting and analyzing the data, and getting team members in the habit of recording some key bits of data about their work. Once you’ve developed a measurement culture in your organization, you’ll be surprised how much you can learn from the data.

Also read Measuring Requirements, Part 1

Jama Software has partnered with Karl Wiegers to share licensed content from his books and articles on our web site via a series of blog posts, whitepapers and webinars.  Karl Wiegers is an independent consultant and not an employee of Jama.  He can be reached at http://www.processimpact.com.  Enjoy these free requirements management resources.

 

Disciplined software organizations collect a focused set of metrics about each of their projects. These metrics provide insight into the size of the product; the effort, time, and money that the project or individual tasks consumed; the project status; and the product’s quality. Because requirements are an essential project component, you should measure several aspects of your requirements engineering activities. This two-part series, adapted from my book More about Software Requirements, describes several meaningful metrics related to requirements activities on your projects.

Product Size

The most fundamental metric is the number of requirements in a body of work. Your project might represent requirements by using a mix of use cases, functional requirements, user stories, feature descriptions, event-response tables, and analysis models. However, the team ultimately implements functional requirements, descriptions of how the system should behave under specific conditions.

Begin your requirements measurement by simply counting the individual functional requirements that are allocated to the baseline for a given product release or development iteration. If different team members can’t count the requirements and get the same answer, you have to wonder what other sorts of ambiguities and misunderstandings they’ll experience. Knowing how many requirements are going into a release will help you judge how the team is progressing toward completion because you can monitor the backlog of work remaining to be done. If you don’t know how many requirements you need to work on, how will you know when you’re done?

Of course, not all functional requirements will consume the same implementation and testing effort. If you’re going to count functional requirements as an indicator of system size, your analysts will need to write them at a consistent level of granularity. One guideline is to decompose high-level requirements until the child requirements are all individually testable. That is, a tester can design a few logically related tests to verify whether a requirement was correctly implemented. Count the total number of child requirements, because those are what developers will implement and testers will test. Alternative requirements sizing techniques include use case points and story points. All of these methods involve estimating the relative effort to implement a defined chunk of functionality.

Functional requirements aren’t the whole story, of course. Stringent nonfunctional requirements can consume considerable design and implementation effort. Some functionality is derived from specified nonfunctional requirements, such as security requirements, so those would be incorporated appropriately into the functional requirement size estimate. But not all nonfunctional requirements will be reflected in this size estimate. Be sure to consider the impact of nonfunctional requirements upon your effort estimate. Consider the following situations:

  • If the user must have multiple ways to access specific functions to improve usability, it will take more development effort than if only one access mechanism is needed.
  • Imposed design and implementation constraints, such as multiple external interfaces to achieve compatibility with an existing operating environment, can lead to a lot of interface work even though you aren’t providing additional new product functionality.
  • Strict performance requirements might demand extensive algorithm and database design work to optimize response times.
  • Rigorous availability and reliability requirements can imply significant work to build in failover and data recovery mechanisms, as well as having implications for the system architecture you select.

You’ll also find it informative to track the growth in requirements as a function of time, no matter what requirements size metric you use. One of my clients found that their projects typically grew in size by about twenty-five percent before delivery. Amazingly, they also ran about twenty-five percent over the planned schedule on most of their projects. Coincidence? I think not.

Requirements Quality

Consider collecting some data regarding the quality of your requirements. Inspections of requirements specifications are a good source of this information. Count the requirements defects you discover and classify them into various categories: missing requirements, erroneous requirements, unnecessary requirements, incompleteness, ambiguities, and so forth. Use defect type frequencies and root-cause analysis to tune up your requirements processes so the team makes fewer of these types of errors in the future. For instance, if you find that missing requirements are a common problem, your elicitation approaches need some adjustments. Perhaps your business analysts aren’t asking enough questions or the right questions, or maybe you need to engage more appropriate user representatives in the requirements development process.

If the team members don’t think they have time to inspect all their requirements documentation, try inspecting a sample of just a few pages. Then calculate the average defect density—the number of defects found per specification page—for the sample. Assuming that the sample was representative of the entire document (a big assumption), you can multiply the number of uninspected pages by this defect density to estimate the number of undiscovered defects that could still lurk in the specification. Less experienced inspectors might discover only, say, half the defects that actually are present, so use this estimated number of undiscovered defects as a lower bound. Inspection sampling can let you assess the document’s quality so that you can determine whether it’s cost effective to inspect the rest of the requirements specification. The answer will almost certainly be yes.

Also, keep records of requirements defects that are identified after the requirements are baselined, such as requirements-related problems discovered during design, coding, and testing. These represent errors that leaked through your quality control filters during requirements development. Calculate the percentage of the total number of requirements errors that the team caught at the requirements stage. Removing requirements defects early is far cheaper than correcting them after the team has already designed, coded, and tested the wrong requirements.

Two informative metrics to calculate from inspection data are efficiency and effectiveness. Efficiency refers to the average number of defects discovered per labor hour of inspection effort. Effectiveness refers to the percentage of the defects originally present in a work product that was discovered by inspection. Effectiveness will tell you how well your inspections (or other requirements quality techniques) are working. Efficiency will tell you what it costs you, on average, to discover a defect through inspection. You can compare that cost with the cost of dealing with requirements defects found later in the project or after delivery to judge whether improving the quality of your requirements is cost effective.

The second article in this series will address metrics related to requirements status, change requests, and the effort expended on requirements development and management activities.

Also read Measuring Requirements, Part 2

Jama Software has partnered with Karl Wiegers to share licensed content from his books and articles on our web site via a series of blog posts, whitepapers and webinars.  Karl Wiegers is an independent consultant and not an employee of Jama.  He can be reached at http://www.processimpact.com.  Enjoy these free requirements management resources.